title: "Change Request Template with Rollback Plan - setya.id"
description: "A change request that gives reviewers what they need to approve it: the reason, the risk, how you'll test it, and how you'll undo it if it goes wrong."
url: https://setya.id/templates/change-request-template
lang: en
---

Template

# Change Request Template with Rollback Plan

A change request that gives reviewers what they need to approve it: the reason, the risk, how you'll test it, and how you'll undo it if it goes wrong.

[Baca dalam Bahasa Indonesia →](https://setya.id/id/templates/template-change-request)

Published 22 November 2026Setya

Most changes go fine. The ones that hurt usually skipped something small. Nobody checked what else depended on the system, the rollback plan said "restore from backup" without knowing how long that takes, or the change landed in the middle of month-end closing.

A good change request turns those questions into part of the form. It also makes approval faster, because reviewers don't have to chase the same details every week.

Write the Rollback First

If you can't say how to undo the change and how long that takes, the change isn't ready for approval.

![The path of a change, from request to close, with a way back](https://setya.id/images/figures/change-flow-en.svg)

## 1. Change Details

Change Details

**Title:** [short and specific, e.g. "Upgrade core switch firmware at head office"]

**Requested by:** [name, team]

**Change owner:** [who does the work]

**Change type:** [Standard / Normal / Emergency]

**Planned window:** [date], [start time] to [end time] [time zone]

**Systems affected:** [services, servers, sites]

## 2. Reason and Expected Result

Reason and Expected Result

**Why:** [the problem or need, in one or two sentences]

**What changes:** [what will be different afterwards]

**If we wait:** [the risk of delaying or not doing it]

## 3. Impact and Risk

A quick way to judge the risk: how many people would notice if it failed, and how hard is it to undo?

Impact and Risk

**Who is affected:** [users, teams, customers]

**Downtime:** [none / expected duration]

**Dependencies:** [systems, interfaces or vendors that rely on this]

**Risk level:** [Low / Medium / High], because [reason]

**What could go wrong:** [the most likely problem, and the worst case]

## 4. Implementation Plan

Write the steps so someone else on the team could follow them at 2 am.

| Step | Action | Who | Time |
| --- | --- | --- | --- |
| 1 | [e.g. Confirm backups and take a config snapshot] | [name] | [22:00] |
| 2 | [e.g. Upgrade the standby unit] | [name] | [22:15] |
| 3 | [e.g. Fail over and upgrade the primary unit] | [name] | [22:45] |
| 4 | [Run the checks in section 5] | [name] | [23:30] |

## 5. Testing and Verification

Testing and Verification

**Tested before:** [where and how, e.g. in staging or on one site first, or why testing wasn't possible]

**Checks after the change:** [e.g. login works, a sample transaction goes through, monitoring is green]

**Success means:** [the result that lets you close the change]

## 6. Rollback Plan

Set the rollback deadline inside the window. If the work runs late, there should still be enough time to undo it before users come back.

Rollback Plan

**Roll back if:** [e.g. any check fails, or the work isn't finished by [time]]

**Decision by:** [who makes the call]

**Steps:** [how to undo it, step by step]

**Time needed:** [how long the rollback takes]

**Point of no return:** [the step after which you can no longer roll back, if there is one]

## 7. Communication and Approval

Communication and Approval

**Notify:** [users, service desk, vendors], using the maintenance announcement

**Approved by:** [system owner], [IT manager], [CAB, if required]

**Date approved:** [date]

For the user notice itself, use the [maintenance announcement template](https://setya.id/templates/maintenance-announcement-template). Larger or riskier changes usually go to the [CAB](https://setya.id/glossary#cab) before approval.

## After the Change

- Record the result: successful, partly successful, or rolled back
- Note anything that didn't go to plan
- If something went wrong, run a short review with the [postmortem template](https://setya.id/templates/postmortem-template)
- Update the documentation and diagrams

Keep Changes Small

Several small changes, each with a clear rollback, are safer than one big change that bundles everything. When something breaks, you know which change caused it.